Sl. No. | Title of Project | Funding Agency | Sanction Amount | PI & CO PI | StartYr/EndYr/Duration | Remarks |
1 | Mix design & testing of building materials for construction of building at NIT Sohra | RITES Ltd. Gurgoan | 1,11,237.00 | Dr. C. Marthong & Dr. D.K Sarma | 19.12.2014 | Completed |
2 | Mix design of M25/ M30/ M35 for RITES for construction of NITM Sohra | RITES Ltd. Gurgoan | 1,01,124.00 | Dr. C. Marthong & Dr. D.K Sarma | 27.01.2015 | Completed |
3 | Vetting of Str. Drawing of the proposed Construction of St. Edmund Hr. Sec. School Shillong | Chriastian Brother's Institution Shillong | 1,65,000.00 | Dr. C. Marthong | 27.01.2015 | Completed |
4 | Testing of construction materials for NEEPCO Ltd, Shillong | NEEPCO Ltd. Shillong | 3,000.00 | Dr. C. Marthong | 24.02.2015 | Completed |
5 | Third quality control for IIM construction CPWD, Shillong | CPWD Shillong | 2,26,452.00 | Dr. C. Marthong & Dr. D.K Sarma | 20.02.2015 | Completed |
6 | Testing of angle section and barbed for providing overhanging wire fencing at Shillong Airport | Airport Aurhority of India, Shillong | 15,000.00 | Dr. C. Marthong & Dr. D.K Sarma | 24.03.2015 | Completed |
7 | Testing of Concrete cubes and construction materials | CPWD Shillong | 9,000.00 | Dr. C. Marthong | 15.07. 2015 | Completed |
8 | Testing of construction materials for NEEPCO Ltd, Shillong | NEEPCO Ltd. Shillong | 8,500.00 | Dr. C. Marthong | 15.07.2015 | Completed |
9 | Testing of construction materials for IIM Construction, CPWD | CPWD Shillong | 21,500.00 | Dr. C. Marthong | 11.09. 2015 | Completed |
10 | Testing of construction materials Aggregate, bricks for CPWD, IIM Construction | CPWD Shillong | 20,500.00 | Dr. C. Marthong | 21.10.2015 | Completed |
11 | Testing of construction materials for NEEPCO Ltd, Shillong | NEEPCO Ltd. Shillong | 3,000.00 | Dr. C. Marthong | 21.12.2015 | Completed |
12 | Checking Str. Design of Super Care Hospital Building Shillong | Supercare Hospital Shillong | 1,01,900.00 | Dr. C. Marthong | 23.12.2015 | Completed |
13 | Testing of concrete cubes and bricks, CPWD B.D Marbaniang | CPWD Shillong | 13,500.00 | Dr. C. Marthong | 16.12.2015 | Completed |
14 | Testing of cement, CPWD, (P.K) | CPWD Shillong | 34,000.00 | Dr. C. Marthong | 07.01.2016 | Completed |
15 | Testing of cement, Moorum & bitumen for CPWD, Shillong, (P.K) | CPWD Shillong | 49,500.00 | Dr. C. Marthong | 15.02.2016 | Completed |
16 | Material Testing (brick, aggregate, boulder, railing) CPWD, Shillong ( Shri B.D. Marbaniang) | CPWD Shillong | 1,74,000.00 | Dr. C. Marthong & Dr. D.K Sarma | 04.5.2016 | Completed |
17 | Material Testing (cement, boulder, water, bitumen), CPWD, Shillong, (Shri B.D. Marbaniang) | CPWD Shillong | 42,000.00 | Dr. C. Marthong | 07.4.2016 | Completed |
18 | Material Testing (cement, steel), CPWD, Shillong, (Shri B.D. Marbaniang) | CPWD Shillong | 37,500.00 | Dr. C. Marthong | 23.5.2016 | Completed |
19 | Material Testing (cement, bricks), CPWD, Shillong, (Shri B.D. Marbaniang) | CPWD Shillong | 37,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 17.02.2016 | Completed |
20 | Material Testing CPWD, Shillong, (Shri B.D. Marbaniang) | CPWD Shillong | 32,000.00 | Dr. C. Marthong | 23.06.2016 | Completed |
21 | Structural Assessment of R.C.C roof slab of Sylvan House, Forest Department | Forest Dept. Govt. of Meghalaya | 57,250.00 | Dr. C. Marthong & Dr. M.L.Patton | 13.05.2016 | Completed |
22 | Assessing the strength og college building of Sngap Syiem College, Mawkyrwat | Sngap Syiem College, Mawkyrwat | 55,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 28.04.2016 | Completed |
23 | Testing of concrete cubes, aggregates and bricks for IIM, Shillong, CPWD (B.D Marbaniang) | CPWD Shillong | 39,000.00 | Dr. C. Marthong | 29.12.2015 | Completed |
24 | Testing of AAC Blocks for PWD, Shillong Superlite AAC blocks Industry | Superlite Ltd. Guwahati | 7,000.00 | Dr. C. Marthong | 26.07.2016 | Completed |
25 | Mix design M25 for NERCCDIP project Govt. Of Meghalaya (Shri B.D. Marbaniang) | ADB-PWD, Meghalaya | 34,500.00 | Dr. C. Marthong | 05.08.2016 | Completed |
26 | Testing of construction materials for IIM Shillong project (Shri B.D. Marbaniang) | CPWD Shillong | 1,66,000.00 | Dr. C. Marthong and Dr. D.K.Sarma | 11.08.2016 | Completed |
27 | Third party quality control for CPWD constructions | CPWD Shillong | 2,04,836.00 | Dr. C. Marthong and D.K.Sarma | 18.07.2018 | Completed |
28 | Third party quality control for CPWD constructions | CPWD Shillong | 1,34,472.00 | Dr. C. Marthong and Dr. D.K.Sarma | 28.07.2016 | Completed |
29 | Testing of construction materials and performing mix design M25 for Power Grid Coorporation Limited | Power Grid, Shillong | 70,500.00 | Dr. C. Marthong | 30.08.2016 | Completed |
30 | Testing of construction materials for construction of CMD's residence for NEEPCO at laitkor, Shillong | NEEPCO Ltd. Shillong | 28,500.00 | Dr. C. Marthong | 07.09.2016 | Completed |
31 | Testing of AAC Blocks for PWD, Shillong Powerlite Industries | Powerlite Ltd. Guwahati | 8,050.00 | Dr. C. Marthong | 07.09.2016 | Completed |
32 | Testing of material for Power Grid Corporation Limited supplier by NECCON Power & Infra Limited, Shillong | Power Grid, Shillong | 17,500.00 | Dr. C. Marthong | 14.09.2016 | Completed |
33 | Testing of materials for CPWD, Shillong for construction of IIM, Shillong | CPWD Shillong | 24,150.00 | Dr. C. Marthong and Dr. D.K.Sarma | 14.09.2016 | Completed |
34 | Testing of material for Power Grid Corporation Limited supplier by NECCON Power & Infra Limited, Shillong | Power Grid, Shillong | 24,150.00 | Dr. C. Marthong | 15.09.2016 | Completed |
35 | Testing of material for Power Grid Corporation Limited supplier by NECCON Power & Infra Limited, Shillong | Power Grid, Shillong | 40,825.00 | Dr. C. Marthong | 26.09.2016 | Completed |
36 | Testing of material for Power Grid Corporation Limited supplier by NECCON Power & Infra Limited, Shillong | Power Grid, Shillong | 3,050.00 | Dr. C. Marthong | 5.10.2016 | Completed |
37 | Testing of material for Power Grid Corporation Limited supplier by NECCON Power & Infra Limited, Shillong | Power Grid, Shillong | 33,350.00 | Dr. C. Marthong | 18.10.2016 | Completed |
38 | Testing of construction materials for NEEPCO Ltd, Shillong | CPWD Shillong | 31,500.00 | Dr. C. Marthong | 18.10.2016 | Completed |
39 | Testing of concrete cubes, aggregates and bricks for IIM, Shillong, CPWD (B.D Marbaniang) | CPWD Shillong | 2,34,000.00 | Dr. C. Marthong | 19.10.2016 | Completed |
40 | Third quality control for IIM construction CPWD, Shillong | CPWD Shillong | 1,53,186.00 | Dr. C. Marthong & Dr. D.K Sarma | 19.10.2016 | Completed |
41 | Third quality control for IIM construction CPWD, Shillong | CPWD Shillong | 1,69,198.00 | Dr. C. Marthong & Dr. D.K Sarma | 19.10.2016 | Completed |
42 | Structural vetting for NRL, Assam | NRL, Assam | 34,500.00 | Dr. C. Marthong & Dr. M.L.Patton | 26.10.2016 | Completed |
43 | Testing of concrete cubes, aggregates and bricks for IIM, Shillong, CPWD (B.D Marbaniang) | CPWD Shillong | 60,500.00 | Dr. C. Marthong | 28.10.2016 | Completed |
44 | Testing of materials for IIMPD. CPWD (B.D Marbaniang) | CPWD Shillong | 1,52,000.00 | Dr. C. Marthong | 01.12.2016 | Completed |
45 | Material testing for power Grid | Power Grid, Shillong | 10,350.00 | Dr. C. Marthong and Dr. S. Sharma | 22.11.2016 | Completed |
46 | Material testing for power Grid | Power Grid, Shillong | 32,200.00 | Dr. C. Marthong | 18.11.2016 | Completed |
47 | Structural Design for AF, (HQ), Shillong Zone | Indian Airforce, Shillong | 4,12,399.00 | Dr. C. Marthong & Dr. M.L.Patton | 01.09.2016 | Completed |
48 | Conducting Mix Design M25 grade for power grid, Teok S/S | Power Grid, Shillong | 34,500.00 | Dr. C. Marthong | 23.12.2016 | Completed |
49 | Conducting Mix Design M25 grade for power grid, Behiding S/S | Power Grid, Shillong | 34,500.00 | Dr. C. Marthong | 23.12.2016 | Completed |
50 | Conducting Mix Design M25 grade for power grid, Sonapur S/S | Power Grid, Shillong | 34,500.00 | Dr. C. Marthong | 23.12.2016 | Completed |
51 | Examination/ Vetting of the structural drawings of Shri R.L Sharma, Jailroad | Power Grid, Shillong | 1,11,000.00 | Dr. C. Marthong | 27.12.2016 | Completed |
52 | Conducting Mix design M25 grade for Power Grid, NERPSIP for S/S | Power Grid, Shillong | 34,500.00 | Dr. C. Marthong | 21.12.2016 | Completed |
53 | Conducting Mix design M25 grade for Power Grid,Mynkre S/S (NERPSIP) | Power Grid, Shillong | 34,500.00 | Dr. C. Marthong | 21.12.2016 | Completed |
54 | Material Testing ( Aggregate) For Power Grid | Power Grid, Shillong | 14,950.00 | Dr. C. Marthong | 04.01.2017 | Completed |
55 | Material Testing (Boulder) For CPWD, IIMPD, Shillong No. Camp/AE-1/ IIMPD/ 2016-17/ 01 dt 03.10.16 | Power Grid, Shillong | 74,750.00 | Dr. C. Marthong | 04.01.2017 | Completed |
56 | Material Testing (Stone Boulder) For CPWD, IIMPD, Shillong No. Camp/AE-1/ IIMPD/ 2016-17/ 01 dt 29.11.16 | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 04.01.2017 | Completed |
57 | Material Testing ( Aggregate & Stone) For CPWD, IIMPD, Shillong | CPWD Shillong | 90,850.00 | Dr. C. Marthong | 04.01.2017 | Completed |
58 | Testing of Steel bars for CPWD, Shillong, IIMPD, Shillong | CPWD Shillong | 54,050.00 | Dr. C. Marthong | 04.01.2017 | Completed |
59 | Testing of Construction Material( Cement, Water, Concrete cubes) for CPWD, Shillong- IIM, Shillong project | CPWD Shillong | 55,200.00 | Dr. C. Marthong & Dr. S. Sharma | 04.01.2017 | Completed |
60 | Material Testing ( Steel) for CPWD, Shillong, IIMPD, Shillong | CPWD Shillong | 64,975.00 | Dr. C. Marthong & Dr. D.K. Sarma | 04.01.2017 | Completed |
61 | Material Testing (Bitumen) for CPWD, Shillong, IIMPD, Shillong | CPWD Shillong | 63,250.00 | Dr. C. Marthong | 04.01.2017 | Completed |
62 | Testing of construction materials( Stone Boulder, Bricks and Water) for CPWD, Shillong- IIMPD Project | CPWD Shillong | 89,700.00 | Dr. C. Marthong & Dr. S.Sharma | 04.01.2017 | Completed |
63 | Material Testing ( Stone Boulder) for CPWD, Shillong, IIMPD Boulder: 23(1)/AE-1/IIMPD/SH/ 2015-16/06 dt 28/05/2015 8 sample | CPWD Shillong | 59,800.00 | Dr. C. Marthong | 04.01.2017 | Completed |
64 | Testing of Material ( Stone Boulder) for CPWD, Shillong, IIMPD Boulder: 23(1)/AE-1/IIMPD/SH/ 2014-15/09 dt 26/05/2015 8 sample | Power Grid, Shillong | 59,800.00 | Dr. C. Marthong | 04.01.2017 | Completed |
65 | Testing of construction material for Power Grid Corporation India ltd. | Power Grid, Shillong | 14,950.00 | Dr. C. Marthong | 20.01.2017 | Completed |
66 | Testing of construction material for CPWD, Shillong | CPWD Shillong | 94,300.00 | Dr. C. Marthong | 20.01.2017 | Completed |
67 | Testing of construction material for CPWD, Shillong | Power Grid, Shillong | 58,650.00 | Dr. C. Marthong | 20.01.2017 | Completed |
68 | Testing of water for Power Grid Corporation India | Power Grid, Shillong | 5,750.00 | Dr. C. Marthong & Dr. S. Sharma | 03.02.2017 | Completed |
69 | Testing of water quality for Power Grid Corporation India | Power Grid, Shillong | 10,350.00 | Dr. C. Marthong & Dr. S. Sharma | 03.02.2017 | Completed |
70 | Testing of construction material and water for Power Grid Corporation India | Power Grid, Shillong | 15,525.00 | Dr. C. Marthong | 03.02.2017 | Completed |
71 | Testing of Cement for CPWD, Shillong | Power Grid, Shillong | 29,325.00 | Dr. C. Marthong | 13.02.2017 | Completed |
72 | Testing of Bricks for Power Grid Corporation India Ltd | Power Grid, Shillong | 12,650.00 | Dr. C. Marthong | 15.02.2017 | Completed |
73 | Construction for pile foundation of 132KV Pasighat- Roing- Tezu- Namsai transmission line | Power Grid, Shillong | 75,660.00 | Dr. C. Marthong and Dr. D.K.Sarma | 27.02.2017 | Completed |
74 | Comstruction of Mawkynrew 33/11KV Substation under NERPSIP, Meghalaya | Power Grid, Shillong | 9,775.00 | Dr. C. Marthong | 27.02.2017 | Completed |
75 | Construction of Boundary wall at Proposed NEEPCO Township, Mawdiangdiang, Shillong | NEEPCO Ltd. Shillong | 3,450.00 | Dr. C. Marthong | 27.02.2017 | Completed |
76 | Velting of Structural Design of MES Buildings | MES, Shillong | 50,000.00 | Dr. C. Marthong | 20.02.2017 | Completed |
77 | Testing of water sample for Power Grid Corporation India Ltd | Power Grid, Shillong | 5,750.00 | Dr. C. Marthong & Dr. S. Sharma | 15.03.2017 | Completed |
78 | Testing of water sample and cement cubes for Power Grid Corporation India Ltd | Power Grid, Shillong | 10,925.00 | Dr. C. Marthong & Dr. S. Sharma | 15.03.2017 | Completed |
79 | Testing of concrete cubes for Construction of Lady Keane College | Lady Keane College, Shillong | 1,725.00 | Dr. C. Marthong | 19.03.2017 | Completed |
80 | Testing of Construction Material (Cement, Boulders & Bricks) for construction of Retaining wall behind Academic Block A | CPWD Shillong | 1,30,525.00 | Dr. C. Marthong & Dr. M.L.Patton | 22.03.2017 | Completed |
81 | Material Testing (cement, bricks, stone & water) for construction of additional landfill and Ancillary work at Marten, Shillong | MPWD Shillong | 22,425.00 | Dr. C. Marthong & Dr. S. Sharma | 15.03.2017 | Completed |
82 | Material testing (Stone, cubes & water) for development of RGIIM campus Shillong | CPWD Shillong | 90,850.00 | Dr. C. Marthong & Dr. S. Sharma | 25.03.2017 | Completed |
83 | Material testing (Steel & cement) for development of RGIIM, campus at Shillong | CPWD Shillong | 73,600.00 | Dr. C. Marthong & Dr. S. Sharma | 27.03.2017 | Completed |
84 | Testing of Concrete Cubes, water & Boulder for construction of new 33/11 KV Mynkre and 33/11 KV Rymbai Substation under NERPSIP Scheme Meghalaya | Power Grid, Shillong | 24,725.00 | Dr. C. Marthong & Dr. S. Sharma | 31.03.2017 | Completed |
85 | testing of Cubes cement for pile foundation of 132 Pasighat- Roing- Tezu- Namsai transmission line | Power Grid, Shillong | 23,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 31.03.2017 | Completed |
86 | Construction of 33/11 KV Rymbai Substation under NERPSIP, Meghalaya | Power Grid, Shillong | 13,800.00 | Dr. C. Marthong | 10.04.2017 | Completed |
87 | Construction work of 33/11 KV New Shillong Substation under NERPSIP Scheme Meghalaya | Power Grid, Shillong | 90,200.00 | Dr. C. Marthong & Dr. S. Sharma | 10.04.2017 | Completed |
88 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong & Dr. M.L.Patton | 10.04.2017 | Completed |
89 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
90 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
91 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong & Dr. M.L.Patton | 10.04.2017 | Completed |
92 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
93 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
94 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong & Dr. M.L.Patton | 10.04.2017 | Completed |
95 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
96 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
97 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 52,350.00 | Dr. C. Marthong & Dr. M.L.Patton | 10.04.2027 | Completed |
98 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
99 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
100 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong & Dr. M.L.Patton | 10.04.2017 | Completed |
101 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
102 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
103 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong & Dr. M.L.Patton | 10.04.2017 | Completed |
104 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
105 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
106 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
107 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong & Dr. M.L.Patton | 10.04.2017 | Completed |
108 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
109 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
110 | Construction of Road, i/c retaining walls site grading and preparation for proposed state of Art Academic cum residential campus of RGIIM at Umsawli, Shillong (Phase- I) | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 10.04.2017 | Completed |
111 | Design of steel building located at Shillong for Neil Sootinck | M/S Neil Sootinck Suting, Shillong | 80,500.00 | Dr. D. Podder Dr. M.L.Patton & Dr. C. Marthong | 22.05.2017 | Completed |
112 | Testing of Cement for CPWD, Shillong | CPWD Shillong | 48,875.00 | Dr. C. Marthong | 22.05.2017 | Completed |
113 | Testing of bricks & Cement cubes | CPWD Shillong | 15,525.00 | Dr. C. Marthong & Dr. M.L.Patton | 22.05.2017 | Completed |
114 | Conducting Mix design NERCCDIIP, Shillong | Power Grid Shillong | 34,500.00 | Dr. C. Marthong | 22.05.2017 | Completed |
115 | Testing of boulder for CPWD, Shillong | CPWD Shillong | 74,750.00 | Dr. C. Marthong | 22.05.2017 | Completed |
116 | Testing of concrete cubes, CPWD | CPWD Shillong | 3,450.00 | Dr. C. Marthong | 22.05.2017 | Completed |
117 | Testing of concrete cubes, CPWD | CPWD Shillong | 17,250.00 | Dr. C. Marthong | 05.06.2017 | Completed |
118 | Testing of concrete cubes, CPWD | CPWD Shillong | 17,250.00 | Dr. C. Marthong | 05.06.2017 | Completed |
119 | Testing of concrete cubes, CPWD | CPWD Shillong | 17,250.00 | Dr. C. Marthong | 05.06.2017 | Completed |
120 | Testing of concrete cubes, PWD | ADB-PWD, Meghalaya | 17,250.00 | Dr. C. Marthong | 05.06.2017 | Completed |
121 | Testing of concrete cubes, PWD | ADB-PWD, Meghalaya | 10,500.00 | Dr. C. Marthong | 06.06.2017 | Completed |
122 | Testing of concrete cubes, PWD | ADB-PWD, Meghalaya | 10,500.00 | Dr. C. Marthong | 06.06.2017 | Completed |
123 | Testing of concrete cubes, CPWD | CPWD Shillong | 10,500.00 | Dr. C. Marthong | 06.06.2017 | Completed |
124 | Testing of concrete cubes, CPWD | CPWD Shillong | 10,500.00 | Dr. C. Marthong | 06.06.2017 | Completed |
125 | Testing of Construction Materials | Indian Airforce, Shillong | 25,000.00 | Dr. C. Marthong | 06.06.2017 | Completed |
126 | Velting of Structural Design & Drawing for N.F. Railway building, Agartala | N.F.Railway Agartala | 10,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 07.06.2017 | Completed |
127 | Testing of cement for SIPMIU. Project Shillong | MPWD Shillong | 9,775.00 | Dr. C. Marthong | 15.06.2017 | Completed |
128 | Testing of Construction Materials | CPWD Shillong | 20,700.00 | Dr. C. Marthong | 15.06.2017 | Completed |
129 | Testing of Construction Materials for SIPMIU, Meghalaya | MPWD Shillong | 17,250.00 | Dr. C. Marthong | 15.06.2017 | Completed |
130 | Testing of bricks, soil, cubes for Power Grid Shillong | Power Grid, Shillong | 40,825.00 | Dr. C. Marthong & Dr. S. Sharma | 05.07.2017 | Completed |
131 | Testing of boulder/ steel/ water/ cement for CPWD, Shillong | CPWD Shillong | 45,712.00 | Dr. S. Sharma & Dr. C. Marthong | 05.07.2017 | Completed |
132 | Structural design for OTM ACCN for Airforce Shillong | Indian Airforce, Shillong | 7,19,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 05.07.2017 | Completed |
133 | Testing of boulder and metal for CPWD, Shillong | CPWD Shillong | 1,19,025.00 | Dr. C. Marthong | 05.07.2017 | Completed |
134 | Testing of aggregate & cement for CPWD, Shillong | CPWD Shillong | 1,19,025.00 | Dr. C. Marthong | 05.07.2017 | Completed |
135 | Testing of boulder for CPWD, Shillong | CPWD Shillong | 2,99,000.00 | Dr. M.L.Patton & Dr. C. Marthong | 05.07.2017 | Completed |
136 | Testing of Construction Materials for Power Grid Corporation of India Limited | Power Grid Shillong | 31,270.00 | Dr. C. Marthong | 30.08.2017 | Completed |
137 | Testing of Construction Materials for Power Grid Corporation of India Limited | Power Grid Shillong | 15,930.00 | Dr. C. Marthong | 30.08.2017 | Completed |
138 | Testing of Construction Materials for Power Grid Corporation of India Limited | Power Grid Shillong | 14,025.00 | Dr. C. Marthong & Dr. S. Sharma | 30.08.2017 | Completed |
139 | Testing of Construction Materials for Donush Siangshai Educational Trust | M/s Donush Siangshai Educational Trust | 21,800.00 | Dr. C. Marthong & Dr. M.L.Patton | 30.08.2017 | Completed |
140 | Testing of Concrete Cubes | CPWD Shillong | 7,080.00 | Dr. C. Marthong | 06.10.2017 | Completed |
141 | Testing of Concrete Cubes & Boulders for CPWD, Shillong | CPWD Shillong | 89,090.00 | Dr. C. Marthong | 06.10.2017 | Completed |
142 | Testing of construction materials, CPWD | CPWD Shillong | 20,355.00 | Dr. C. Marthong | 25.09.2017 | Completed |
143 | Testing of construction materials RITES Ltd. | RITES Ltd. Shillong | 10,030.00 | Dr. C. Marthong & Dr. M.L.Patton | 27.09.2017 | Completed |
144 | Design and Renovation of Sylvan House, Forest Dept. Govt. of Meghalaya | Forest Dept. Govt. of Meghalaya | 1,01,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 09.10.2017 | Completed |
145 | Design and Estimate for the inclined pitch roof slab roof "Sylvan House Building". | Forest Dept. Govt. of Meghalaya | 1,01,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 07.11.2017 | completed |
146 | Testing of cement for RITES, Sohra | RITES, Sohra | 10,030.00 | Dr. C. Marthong | 07.11.2017 | completed |
147 | Testing of Concrete Cubes ,cement and water for CPWD Shillong. | CPWD Shillong. | 20,355.00 | Dr. C. Marthong & S.Sharma | 07.11.2017 | completed |
148 | Testing of Concrete Cubes ,cement ,coarse agg., fine agg and steel for CPWD Shillong. | CPWD Shillong. | 70,800.00 | Dr. C. Marthong | 07.11.2017 | completed |
149 | Testing of Concrete Cubes and cement for Power Grid Corporation India Ltd,Shillong | Power Grid Corporation India Ltd,Shillong | 27,730.00 | Dr. C. Marthong | 07.11.2017 | completed |
150 | Testing of Concrete Cubes and steel for North East Consultancy Services, Shillong. | North East Consultancy Services, Shillong. | 13,570.00 | Dr. C. Marthong | 07.11.2017 | completed |
151 | Testing of Boulders and Bricks for CPWD Shillong. | CPWD Shillong. | 1,53,530.00 | Dr. C. Marthong | 04.12.2017 | completed |
152 | Testing of cement for CPWD Shillong. | CPWD Shillong. | 20,060.00 | Dr. C. Marthong | 04.12.2017 | completed |
153 | Testing of Pavement materials and GSB mix design for AAI, Shillong. | AAI, Shillong. | 21,500.00 | Dr. C. Marthong & Dr. M.L.Patton | 04.12.2017 | completed |
154 | Testing of Pavement materials and GSB mix design for AAI, Shillong. | AAI, Shillong. | 31,010.00 | Dr. C. Marthong | 04.12.2017 | completed |
155 | Testing of Concrete Cubes and water for Power Grid Corporation India Ltd,Shillong | Power Grid Corporation India Ltd,Shillong | 23,600.00 | Dr. C. Marthong & S.Sharma | 04.12.2017 | completed |
156 | Testing of Concrete Cubes for BD Marbaniang,Shillong | CPWD Shillong. | 5,310.00 | Dr. C. Marthong & Dr. M.L.Patton | 04.12.2017 | completed |
157 | Testing of Concrete Cubes for Power Grid Corporation India Ltd,Shillong | Power Grid Corporation India Ltd,Shillong | 5,310.00 | Dr. C. Marthong | 17.01.2018 | completed |
158 | Testing of AAC blocks for St. Edmund college campus, Shillong. | St. Edmund college campus, Shillong. | 28,085.00 | Dr. C. Marthong | 17.01.2018 | completed |
159 | Testing of Concrete Cubes ,cement ,coarse agg., fine agg and bricks for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 47,790.00 | Dr. C. Marthong | 17.01.2018 | completed |
160 | Testing of Steel for CPWD Shillong. | CPWD Shillong. | 1,13,280.00 | D.K Sharma | 17.01.2018 | completed |
161 | Testing of Boulders, water and cement for CPWD Shillong. | CPWD Shillong. | 5,44,570.00 | Dr. C. Marthong, S.Sharma & Dr. M.L.Patton | 17.01.2018 | completed |
162 | Testing of Concrete Cubes ,cement , fine agg ,steel, water and bricks for DRDA, west khasi hills district, Shillong. | DRDA, west khasi hills district, Shillong. | 74,930.00 | Dr. C. Marthong & D.k Sharma | 05.02.2018 | completed |
163 | Testing of Concrete Cubes ,cement , fine agg ,steel, water and bricks for DRDA, west khasi hills district, Shillong. | DRDA, west khasi hills district, Shillong. | 74,930.00 | Dr. C. Marthong & D.k Sharma | 05.02.2018 | completed |
164 | Testing of ,cement , fine agg ,coarse agg and water for Blackberry Overseas Put Ltd. | Blackberry Overseas Put Ltd. | 60,700.00 | Dr. C. Marthong | 17.01.2018 | completed |
165 | Testing of Boulders ,water and cement for CPWD Shillong. | CPWD Shillong. | 3,58,130.00 | Dr. C. Marthong, S.Sharma & Dr. M.L.Patton | 17.01.2018 | completed |
166 | Testing of Concrete Cubes and cement for Power Grid Corporation India Ltd,Shillong | Power Grid Corporation India Ltd,Shillong | 33,040.00 | Dr. C. Marthong | 17.01.2018 | completed |
167 | Testing of ,water and cement for CPWD Shillong. | CPWD Shillong. | 6,785.00 | S.Sharma | 17.01.2018 | completed |
168 | Testing of Concrete Cubes and cement for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 11,800.00 | Dr. C. Marthong | 05.02.2018 | completed |
169 | Testing of Bricks & FLAG for HSCC(India) Ltd NEIGRIHMS | HSCC(India) Ltd NEIGRIHMS | 6,372.00 | Dr. C. Marthong | 26.02.2018 | completed |
170 | Testing of Concrete Cubes,bricks and cement for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 34,810.00 | Dr. C. Marthong & Dr. M.L.Patton | 01.02.2018 | completed |
171 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 3,540.00 | Dr. C. Marthong | 01.02.2018 | completed |
172 | Testing of Concrete Cubes and steel for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 37,170.00 | Dr. C. Marthong & D.k Sharma | 14.02.2018 | completed |
173 | Testing of Boulders ,coarse agg. and cement for CPWD Shillong. | Testing of Boulders ,coarse agg. and cement for CPWD Shillong. | 2,05,320.00 | Dr. C. Marthong | 14.02.2018 | completed |
174 | Testing of Boulders for CPWD Shillong. | Testing of Boulders for CPWD Shillong. | 5,75,250.00 | Dr. C. Marthong & Dr. M.L.Patton | 14.02.2018 | completed |
175 | Testing of Concrete Cubes and cement for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 18,900.00 | Dr. C. Marthong | 14.02.2018 | completed |
176 | Testing of Boulders ,coarse agg. and cement for CPWD Shillong. | CPWD Shillong. | 2,88,514.00 | Dr. C. Marthong & Dr. M.L.Patton | 26.02.2018 | completed |
177 | Testing of Concrete Cubes and cement for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 22,420.00 | Dr. C. Marthong & Dr. M.L.Patton | 26.02.2018 | completed |
178 | Testing of ,coarse agg., fine agg.,steel ,concrete cubes and cement for NERCC DIP Shillong. | NERCC DIP Shillong. | 73,750.00 | Dr. C. Marthong & D.k Sharma | 06.03.2018 | completed |
179 | Testing of Concrete Cubes,fine agg.,bricks and cement for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 59,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 06.03.2018 | completed |
180 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 19,470.00 | Dr. C. Marthong | 06.03.2018 | completed |
181 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 17,770.00 | Dr. C. Marthong | 26.03.2018 | completed |
182 | Testing of Boulders ,bricks,concrete cubes and cement for CPWD Shillong. | CPWD Shillong. | 1,91,160.00 | Dr. C. Marthong & S.Sahoo | 26.03.2018 | completed |
183 | Vetting of structural Design and Drawings of the proposed OT complex for Nazareth ,Shillong | Nazareth ,Shillong | 11,800.00 | Dr. C. Marthong | 26.03.2018 | completed |
184 | Vetting of structural Design for Pine Mount International School at Doldegre,Meghalaya. | MPWD Shillong | 23,580.00 | Dr. C. Marthong & Dr. M.L.Patton | 26.03.2018 | completed |
185 | Testing of Boulders ,coarse agg. and cement for CPWD Shillong. | CPWD Shillong | 5,01,500.00 | Dr. C. Marthong & Dr. M.L.Patton | 12.04.2018 | completed |
186 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 10,620.00 | Dr. C. Marthong & S.Sahoo | 12.04.2018 | completed |
187 | Testing of coarse agg.for NCC Kolkata | Testing of coarse agg.for NCC Kolkata | 5,900.00 | Dr. C. Marthong | 12.04.2018 | completed |
188 | Testing of Cement for PGCIL, Shillong. | Testing of Cement for PGCIL, Shillong. | 18,360.00 | Dr. C. Marthong & Dr. M.L.Patton | 12.04.2018 | completed |
189 | Testing of Concrete Cubes and Cement for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 27,000.00 | Dr. C. Marthong & S.Sahoo | 12.04.2018 | completed |
190 | Testing of Cement for RITESLtd. | RITESLtd. | 20,060.00 | Dr. C. Marthong & Dr. M.L.Patton | 07.05.2018 | completed |
191 | Testing of Concrete Cubes ,Cement and mix design for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 77,290.00 | Dr. C. Marthong & Dr. M.L.Patton | 07.05.2018 | completed |
192 | Testing of Boulders ,concrete cubes , water. and cement for CPWD Shillong. | CPWD Shillong | 4,33,945.00 | Dr. C. Marthong | 07.05.2018 | completed |
193 | Testing of Cement for RITESLtd. | Testing of Cement for RITESLtd. | 10,030.00 | Dr. C. Marthong & Dr. M.L.Patton | 07.05.2018 | completed |
194 | Structural design of OTM ACCN for ALH SQN (PH-11) at Dinjan Miltary station (Job no: E/1994) | MES Shillong | 6,90,000.00 | Dr. C. Marthong & Dr. M.L.Patton | 07.05.2018 | completed |
195 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 3,540.00 | Dr. C. Marthong | 29.05.2018 | completed |
196 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 12,390.00 | Dr. C. Marthong & Dr. M.L.Patton | 29.05.2018 | completed |
197 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 7,080.00 | Dr. C. Marthong | 29.05.2018 | completed |
198 | Mix design for M/S Blackberry Put Ltd. | M/S Blackberry Put Ltd. | 35,400.00 | Dr. C. Marthong | 29.05.2018 | completed |
199 | Testing of Concrete Cubes ,Cement and bricks for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 57,820.00 | Dr. C. Marthong & Dr. M.L.Patton | 29.05.2018 | completed |
200 | Testing of Boulders, fine agg. And cement for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 16,520.00 | Dr. C. Marthong | 29.05.2018 | completed |
201 | Testing of Cement for RITES Ltd. | Testing of Cement for RITES Ltd. | 10,030.00 | Dr. C. Marthong | 28.06.2018 | completed |
202 | Testing of water for CPWD Shillong. | CPWD Shillong | 6,785.00 | S.Sharma | 28.06.2018 | completed |
203 | Testing of Cement for RITES Ltd. | RITES Ltd. | 10,030.00 | Dr. C. Marthong | 28.06.2018 | completed |
204 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 7,080.00 | Dr. C. Marthong & Dr. M.L.Patton | 28.06.2018 | completed |
205 | Testing of Cement for NIT Meghalaya. | NIT Meghalaya. | 20,060.00 | Dr. C. Marthong | 19-06-2018 | completed |
206 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 36,580.00 | Dr. C Marthong & Dr. ML Patton | 27.08.2018 | completed |
207 | Testing of Coarse agg., Fine agg. & Cement for NERCCDIP, Meghalaya | NERCCDIP, Meghalaya | 20,650.00 | Dr. C Marthong & Dr. ML Patton | 27.08.2018 | completed |
208 | Testing of concrete beams for Airport Authority of India, Shillong | Airport Authority of India, Shillong | 7,080.00 | Dr C Marthong | 27.08.2018 | completed |
209 | Testing of concrete cubes for NERCCDIP, Meghalaya | NERCCDIP, Meghalaya | 3,540.00 | Dr C Marthong | 27.08.2018 | completed |
210 | Testing of cement for CPWD Shillong. | CPWD Shillong | 40,120.00 | Dr. C Marthong & Dr. ML Patton | 27.08.2018 | completed |
211 | Testing of cement and concrete cubes for CPWD Shillong | CPWD Shillong | 27,140.00 | Dr. C. Marthong | 27.08.2018 | completed |
212 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 10,620.00 | Dr. C. Marthong | 27.08.2018 | completed |
213 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 8,850.00 | Dr. C Marthong | 03.10.2018 | completed |
214 | Testing of concrete cubes for St Teresa International School, Shillong | St Teresa International School, Shillong | 2,000.00 | Dr. C Marthong | 03.10.2018 | completed |
215 | Testing of cement for CPWD Shillong. | CPWD Shillong | 10,030.00 | Dr. C Marthong & Dr. ML Patton | 03.10.2018 | completed |
216 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 10,620.00 | Dr. C Marthong & Dr. ML Patton | 03.10.2018 | completed |
217 | Testing of Coarse Agg. Bricks for PGCIL, Shillong | Power Grid Corporation India Ltd,Shillong | 20,650.00 | Dr. C Marthong | 03.10.2018 | completed |
218 | Testing of Cement for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 10,030.00 | Dr. C Marthong & Dr. ML Patton | 03.10.2018 | completed |
219 | Testing of Fine agg, Coarse agg & Cement for PGCIL, Shillong | Power Grid Corporation India Ltd,Shillong | 64,310.00 | Dr. C Marthong | 05.11.2018 | completed |
220 | Testing of Concrete Core cutting samples for PGCIL, Shillong | Power Grid Corporation India Ltd,Shillong | 37,170.00 | Dr. C Marthong & Dr. ML Patton | 05.11.2018 | completed |
221 | Testing of Vrick, Cement, Concrete cube & water for CPWD, Shillong | CPWD Shillong | 52,805.00 | Dr. C Marthong & Dr. S Sharma | 05.11.2018 | completed |
222 | Testing of Bricks , Cement, concrete cubes for PGCIL, Shillong | Power Grid Corporation India Ltd,Shillong | 40,120.00 | Dr C Marthong | 03.12.2018 | completed |
223 | Vetting of structural design for NEIAH, Shillong | r NEIAH, Shillong | 1,47,500.00 | Dr. C Marthong & Dr. ML Patton | 03.12.2018 | completed |
224 | Vetting of DPR "Greater Sohra water supply" scheme for PHE, Govt. of Meghalaya | PHE, Govt. of Meghalaya | 18,75,000.00 | Dr. C Marthong, Dr. H M Kalita, Dr. D Podder & Dr. D Adak | 05.11.2018 | completed |
225 | Vetting of DPR "Laying of new feeder mains under Tura Phase- I&II water supply scheme, Govt. of Meghalaya | PHE, Govt. of Meghalaya | 26,24,250.00 | Dr. C Marthong, Dr. H M Kalita, Dr. D Podder & Dr. D Adak | 05.11.2018 | completed |
226 | Testing of cement, concrete cubes for PGCIL Shillong | Power Grid Corporation India Ltd,Shillong | 30,680.00 | Dr. C Marthong | 23.01.2019 | completed |
227 | Testing of cement, concrete cubes for PGCIL Shillong | Power Grid Corporation India Ltd,Shillong | 33,630.00 | Dr. C Marthong | 23.01.2019 | completed |
228 | Testing of cement, concrete cubes for PGCIL Shillong | Power Grid Corporation India Ltd,Shillong | 27,140.00 | Dr. C Marthong | 23.01.2019 | completed |
229 | Testing of cement, concrete cubes for PGCIL Shillong | Power Grid Corporation India Ltd,Shillong | 40,170.00 | Dr. C Marthong | 23.01.2019 | completed |
230 | Testing of bricks, concrete cube for PGCIL, Shillong | Power Grid Corporation India Ltd,Shillong | 27,730.00 | Dr. C Marthong | 19.02.2019 | completed |
231 | Testing of concrete cube, fine agg, coarse agg. For NERCCDIP, Shillong | NERCCDIP, Shillong | 31,860.00 | Dr. C Marthong | 19.02.2019 | completed |
232 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 12,390.00 | Dr. C Marthong | 19.02.2019 | completed |
233 | Cantontment Board, Shillong | Cantontment Board, Shillong | 1,00,000.00 | Dr. C Marthong & Dr. ML Patton | 09.10.2019 | Completed |
234 | Testing of cement & concrete cubes for PGCIL, Shillong | Testing of cement & concrete cubes for PGCIL, Shillong | 20,650.00 | Dr. C Marthong | 18.03.2019 | completed |
235 | Testing of Cement for PGCIL, Shillong. | Testing of Cement for PGCIL, Shillong. | 40,120.00 | Dr. C Marthong | 22.03.2019 | completed |
236 | Testing of Concrete Cubes for PGCIL, Shillong. | Power Grid Corporation India Ltd,Shillong | 8,850.00 | Dr. C Marthong | 22.03.2019 | completed |
237 | Testing of cement for construction of NEIAH, Shillong, Phase-II | NEIAH, Shillong, Phase-II | 11,033.00 | Dr. C Marthong | 24.04.2019 | completed |
238 | Cement Testing for Construction of proposed 33/11 kV Mawpat S/s (415 bags) | Power Grid Corporation India Ltd,Shillong | 20,060.00 | Dr. C Marthong | 24.04.2019 | completed |
239 | Testing of boulder, water for CPWD, Shillong IIM Shillong | CPWD Shillong | 3,43,321.00 | Dr. C Marthong & Dr. S. Sharma | 10.06.2019 | completed |
240 | Testing of cement & cubes for Construction of proposed 220/132/33kV New Shillong | Power Grid Corporation India Ltd,Shillong | 42,480.00 | Dr. C Marthong | 24.04.2019 | completed |
241 | Testing of cubes for construction of additional land fill area of 8500 sq.m | MPWD Shillong | 3,540.00 | Dr. C Marthong | 24.04.2019 | completed |
242 | Testing of cement for construction of boundary wall for the additionalmland of NIT, Meghalaya | NIT, Meghalaya | 11,033.00 | Dr. C Marthong | 24.04.2019 | completed |
243 | Material testing for Construction of under ground Reservior, Pump House, internal water supply etc.in the campus of IIM, Shillong | CPWD Shillong | 44,160.00 | Dr. C Marthong | 24.04.2019 | completed |
244 | Testing of cubes for construction of Shillong Government College, Shillong | Government College, Shillong | 7,680.00 | Dr. C Marthong | 24.04.2019 | completed |
245 | Testing of Construction materials for Power Grid under NERPSIP Scheme, Shillong | Power Grid Corporation India Ltd,Shillong | 55,165.00 | Dr. C Marthong | 10.06.2019 | completed |
246 | Testing of Cube sample for Power Grid, New Shillong GIS(Meg- SS-02), NERPSIP | Power Grid Corporation India Ltd,Shillong | 11,682.00 | Dr. C Marthong | 10.06.2019 | completed |
247 | Vetting/ Design of Structures draw bonded warehouse godown Lad Rymbai | Lad Rymbai | 6,000.00 | Dr. C Marthong | 10.06.2019 | completed |
248 | Testing of Boulder for CPWD, Shillong | CPWD Shillong | 5,75,250.00 | Dr. C Marthong & Dr. ML Patton | 17.06.2019 | completed |
249 | Testing of concrete cubes, Power Grid corporation of India | Power Grid Corporation India Ltd,Shillong | 38,940.00 | Dr. C Marthong | 16.08.2019 | completed |
250 | Testing of concrete cubes, Power Grid corporation of India | Power Grid Corporation India Ltd,Shillong | 11,682.00 | Dr. C Marthong | 16.08.2019 | completed |
251 | Testing of construction materials, CPWD, Shillong | Testing of construction materials, CPWD, Shillong | 55,814.00 | Dr. C Marthong | 16.08.2019 | completed |
252 | Testing of construction materials, Meghalaya Information technology Society, Shillong | Meghalaya Information technology Society, Shillong | 67,500.00 | Dr. C Marthong | 16.08.2019 | completed |
253 | Concrete mix design, IRCON Infrastructure & Service Ltd. at Dawki, Meghalaya | IRCON Infrastructure & Service Ltd. at Dawki, Meghalaya | 44,781.00 | Dr. C Marthong | 16.08.2019 | completed |
254 | Testing of construction materials, Power Grid corporation of India | Power Grid Corporation India Ltd,Shillong | 37,347.00 | Dr. C Marthong | 16.08.2019 | completed |
255 | Tesing of construction materials, PGCIL Shillong | Power Grid Corporation India Ltd,Shillong | 38,291.00 | Dr. C Marthong & Dr. ML Patton | 16.08.2019 | completed |
256 | Testing of construction materials, Power Grid corporation of India | Power Grid Corporation India Ltd,Shillong | 22,066.00 | Dr. C Marthong & Dr. ML Patton | 01.10.2019 | completed |
257 | Structural Assessment of M/s Marrinette Challam building, Garikhana, lamavilla, Shillong | M/s Marrinette Challam building, Garikhana, lamavilla, Shillong | 6,000.00 | Dr. C Marthong | 01.10.2019 | completed |
258 | Structural Design, MES Shillong | MES Shillong | 6,85,224.00 | Dr. C Marthong & Dr. ML Patton | 01.10.2019 | completed |
259 | Testing of construction materials, Power Grid Corporation of India | Power Grid Corporation India Ltd,Shillong | 11,682.00 | Dr. C Marthong & Dr. ML Patton | 06.11.2019 | completed |
260 | Testing of construction materials, CPWD Shillong | CPWD Shillong | 82,836.00 | Dr. C Marthong | 06.11.2019 | completed |
261 | Testing of construction materials, CPWD Shillong | CPWD Shillong | 44,132.00 | Dr. C Marthong | 06.11.2019 | completed |
262 | Testing of construction materials, CPWD Shillong | CPWD Shillong | 33,099.00 | Dr. C Marthong | 06.11.2019 | completed |
263 | Testing of water, CPWD Shillong | CPWD Shillong | 6,490.00 | Dr. C Marthong & Dr. ML Patton | 06.11.2019 | completed |
264 | Testing of construction materials, CPWD Shillong | CPWD Shillong | 8,850.00 | Dr. C Marthong & Dr. ML Patton | 06.11.2019 | completed |
265 | Concrete mix design, CPWD Shillong | CPWD Shillong | 44,160.00 | Dr. C Marthong & Dr. ML Patton | 06.11.2019 | completed |
266 | Testing of construction materials, Power Grid Corporation of India | Power Grid Corporation India Ltd,Shillong | 14,160.00 | Dr. C Marthong & Dr. ML Patton | 20.12.2019 | completed |
267 | Testing of construction materials, Power Grid Corporation of India | Power Grid Corporation India Ltd,Shillong | 99,946.00 | Dr. C Marthong | 20.12.2019 | completed |
268 | Testing of construction materials, Power Grid Corporation of India | Power Grid Corporation India Ltd,Shillong | 7,788.00 | Dr. C Marthong | 20.12.2019 | completed |
269 | Testing of construction materials, Power Grid Corporation of India | Power Grid Corporation India Ltd,Shillong | 19,470.00 | Dr. C Marthong | 17.01.2020 | completed |
270 | Concrete mix design, MPWD Shillong | MPWD Shillong | 44,781.00 | Dr. C Marthong | 29.01.2020 | completed |
271 | Testing of construction materials, MPWD Shillong | MPWD Shillong | 34,397.00 | Dr. C Marthong | 29.01.2020 | completed |
272 | NDT Tesing, NERPSIP Meghalaya | Power Grid Corporation India Ltd,Shillong | 44,781.00 | Dr. C Marthong & Dr. ML Patton | 29.01.2020 | completed |
273 | Concrete mix design, MPWD Shillong | MPWD Shillong | 44,160.00 | Dr. C Marthong | 29.01.2020 | completed |
274 | Concrete mix design, MPWD Shillong | Concrete mix design, MPWD Shillong | 44,781.00 | Dr. C Marthong | 29.01.2020 | completed |
275 | Vetting of Estimate and structural design, construction of traditional indistry with furnitures cum skill development center, Mawkyllei, West Khasi Hills. | MPWD Shillong | 82,600.00 | Dr. C Marthong | 29.01.2020 | completed |
276 | Testing of construction materials, Atomic Minerals Directorate for Exploration & research (NER), Shillong | Atomic Minerals Directorate for Exploration & research (NER), Shillong | 5,310.00 | Dr. C Marthong | 06.03.2020 | completed |
277 | Testing of construction materials, CPWD Shillong | CPWD Shillong | 1,19,416.00 | Dr. C Marthong | 06.03.2020 | completed |
278 | Testing of construction materials, CPWD Shillong | CPWD Shillong | 6,490.00 | Dr. C Marthong | 06.03.2020 | completed |
279 | Testing of construction materials, NERIE, Umiam, Shillong | NERIE, Umiam, Shillong | 25,665.00 | Dr. C Marthong | 06.03.2020 | completed |
280 | Structural design of extension of Chriastian Youth Center Annex Building, Laitumkhrah Presbyterian Church, Shillong | Laitumkhrah Presbyterian Church, Shillong | 45,000.00 | Dr. C Marthong | 06.03.2020 | completed |
281 | Construction of Additional landfill Area of 8500 sqm and Ancillary works (Phase 2) at Marten, Shillong, package no. NERCCDIP/TR-02/SHG/SWM/04 (Testing of Steel) | SIPMIU, Shillong | 47,790.00 | Dr. Deba Kumar Sarma | 13.02.2019 | Completed |
282 | Conducting test for the works "Construction of Garage cum Workshop shed and Staff Rest Room (Balance works) under Tranche- II at old Landfill site at Marten Shillong" | SIPMIU, Shillong | 24,980.00 | Dr. Deba Kumar Sarma | 19.01.2017 | Completed |
283 | Conducting test for the works "Construction of Garage cum Workshop shed and Staff Rest Room (Balance works) under Tranche- II at old Landfill site at Marten Shillong" | SIPMIU, Shillong | 15,870.00 | Dr. Deba Kumar Sarma | 21.02.2017 | Completed |
284 | Construction of Academic Block, Hostel Buliding cum Dining Hall and 63 Residential Quarters (18 Type I, 18 Type II, 18 Type III, 8 Type V and Director's Bungalow) including internal water supply, sanitary installation and internal electrical installation for RGIIM at Shillong (Phase I) Testing & Alluminism Section | CPWD, Shillong , Meghalaya | 11,800.00 | Dr. Deba Kumar Sarma | 12.09.2017 | Completed |
285 | Construction of RCC & RR Masonsy Retaining walls, gates, parking, under ground tank, covered corridor, external water supply, external fire fighting, Sewerage, Draining systems, Intake pumps, Field Area, Site Grading, Signages and other ancillary works for NIT Meghalaya | RITES Limited | 26,550.00 | Dr. Deba Kumar Sarma | 30.10.2017 | Completed |
286 | Testing of the H.S.D. TMT Bars sizes (8 mm, 10 mm, 12 mm, 16 mm, 28 mm & 25 mm) | P.W.D. (B), Meghalaya, Shillong | 56,640.00 | Dr. Deba Kumar Sarma | 31.10.2017 | Completed |
287 | Rod Testing for "St. Teresa International School" | Donvsh Siangshai Educational Trust | 37,800.00 | Dr. Deba Kumar Sarma | 24.10.2017 | Completed |
288 | Testing of steel for the work development of Rajiv Gandhi Indian Institute of Management at Umsawali, Shillong (SH: Construction of RCC overload Water Tank and Water Body) | CPWD, Dhankheti, Shillong -793003 | 1,13,280.00 | Dr. Deba Kumar Sarma | 26.12.2017 | Completed |
289 | Testing of Aluminium (Sections) for Construction of Auditorium, Boys Hostel and Girls Hostel (Single Seater), Boys hostel (three seater, Director's Bungalow, Guest House, Residential type D & E etc of NIT Meghalaya at Sohra (Cherrapunjee) | RITES Limited | 23,600.00 | Dr. Deba Kumar Sarma | 25.01.2018 | Completed |
290 | Testing of Structural Steel "for the work" Development of RGSSM Campus at Shillong. SH: Construction of RCC overload Water Tank and Water Bodies." | CPWD, Shillong , Meghalaya | 35,400.00 | Dr. Deba Kumar Sarma | 23.03.2018 | Completed |
291 | Construction of RCC & RR Masonsy Retaining walls, gates, parking, under ground tank, covered corridor, external water supply, external fire fighting, Sewerage, Draining systems, Intake pumps, Field Area, Site Grading, Signages and other ancillary works for NIT Meghalaya | RITES Limited | 55,460.00 | Dr. Deba Kumar Sarma | 26.04.2018 | Completed |
292 | Conducting test for the works "Procurement of Equipment for Landfill Site and Compost Plant, Shillong- Inspection of Skid Steer loader SSL 155 with solid tyre" | State Investment Project Management and Implementation Unit (SPIMIU), Shillong | 82,600.00 | Dr. Deba Kumar Sarma | 28.08.2018 | Completed |
293 | Conducting test for the works "Construction of Additional Landfill Area of 8500 Sqm and Ancillary Works (Phase 2) | State Investment Project Management and Implementation Unit (SPIMIU), Shillong | 47,790.00 | Dr. Deba Kumar Sarma | 27.07.2017 | Completed |
294 | Testing of TMT for the Work: "C/o Building for JNV (ph-B) at Nongstoin, Distt: West Khasi Hills Meghalaya (SH: C/o 1nos Girls Dormitory 0.25 with Warden qtrs i/c, W/S & S/S and internal E/I | CPWD, Shillong , Meghalaya | 37,760.00 | Dr. Deba Kumar Sarma | 10.09.2018 | Completed |
295 | Construction of Shillong Government College of Engineering at Shillong, East Khasi Hills Meghalaya | PWD (B) Government of Meghalaya | 56,640.00 | Dr. Deba Kumar Sarma | 22.01.2019 | Completed |
296 | Testing of Steel materials used for construction of bridges on Nongiri to Misei road under PMGSY Package no. : MG/07/03/01 | Executive Engineer (T/C) PWD (Roads) Western Circle cum DPIU, PMGSY, West Khasi Hills | 51,920.00 | Dr. Deba Kumar Sarma | 18.03.2019 | Completed |
297 | Testing of Steel Rod used for construction of Bridges on a road from Umdong to Jaiaw under PMGSY Package No. MG/07/03/44 | Executive Engineer (T/C) PWD (Roads) Western Circle cum DPIU, PMGSY, West Khasi Hills | 63,720.00 | Dr. Deba Kumar Sarma | 20.03.2019 | Completed |
298 | Testing of Steel for "Construction of Boundary wall for the additional land of NIT Meghalaya at Sohra ( Cherrapunjee) - Plot No. 258 Group No. 11" reg | M/s Victor Suja for the work of NIT Meghalaya | 47,200.00 | Dr. Deba Kumar Sarma | 09.04.2019 | Completed |
299 | Construction of Additional landfill Area of 8500 sqm and Ancillary works (Phase 2) at Marten, Shillong, package no. NERCCDIP/TR-02/SHG/PH 2/SWM/04 (Testing of Steel) | M/S B.D. Marbaniang | 8,850.00 | Dr. Deba Kumar Sarma | 05.04.2019 | Completed |
300 | Construction of under Ground Reservior, Pump House, Internal Water supply, approach Road, Developement of right side LCS-1 and retaining wall near water treatment plant in the Campus of IIM Shillong at Umsawli, New Shillong Township, Shillong, Meghalaya | CPWD, Shillong , Meghalaya | 89,680.00 | Dr. Deba Kumar Sarma | 29.07.2019 | Completed |
301 | Balanced development work surrounding the Academic Block 63 Nos. Residential Quaters, Dinning Block and Water Bodies in the Campus of IIM Shillong at Umsawli, New Shillong Township, Shillong | CPWD, Shillong , Meghalaya | 49,560.00 | Dr. Deba Kumar Sarma | 15.10.2019 | Completed |
302 | Construction of Regional Labour Institute of Shillong, Meghalaya (SH: C/o Office Building (G+3), hosted Building (G+3), i/c internal water supply, sanitary installation, rataining wall, underground sump, tablewell, allied civil development work internal electrical installation and fans, first aid hose red, life DG sel, streat, lighting and electrical service connection | CPWD, Shillong , Meghalaya | 77,880.00 | Dr. Deba Kumar Sarma | 15.10.2019 | Completed |
303 | Construction of Regional Labour Institute of Shillong, Meghalaya (SH: C/o Office Building (G+3), hosted Building (G+3), i/c internal water supply, sanitary installation, rataining wall, underground sump, tablewell, allied civil development work internal electrical installation and fans, first aid hose red, life DG sel, streat, lighting and electrical service connection | CPWD, Shillong , Meghalaya | 54,280.00 | Dr. Deba Kumar Sarma | 15.10.2019 | Completed |
304 | Construction of Regional Labour Institute of Shillong, Meghalaya (SH: C/o Office Building (G+3), hosted Building (G+3), i/c internal water supply, sanitary installation, rataining wall, underground sump, tablewell, allied civil development work internal electrical installation and fans, first aid hose red, life DG sel, streat, lighting and electrical service connection | CPWD, Shillong , Meghalaya | 28,320.00 | Dr. Deba Kumar Sarma | 15.10.2019 | Completed |
305 | Construction of Regional Labour Institute of Shillong, Meghalaya (SH: C/o Office Building (G+3), hosted Building (G+3), i/c internal water supply, sanitary installation, rataining wall, underground sump, tablewell, allied civil development work internal electrical installation and fans, first aid hose red, life DG sel, streat, lighting and electrical service connection | CPWD, Shillong , Meghalaya | 49,560.00 | Dr. Deba Kumar Sarma | 15.10.2019 | Completed |
306 | Testing of Steel for the work: "Construction of Commerical complex of Shri Mohendra Rapang at M.G. Road Shillong | M/s Rishen Rapsang | 77,880.00 | Dr. Deba Kumar Sarma | 14.10.2019 | Completed |
307 | Construction of under Ground Reservior, Pump House, Internal Water supply, approach Road, Developement of right side LCS-1 and retaining wall near water treatment plant in the Campus of IIM Shillong at Umsawli, New Shillong Township, Shillong, Meghalaya | CPWD, Shillong , Meghalaya | 14,160.00 | Dr. Deba Kumar Sarma | 14.10.2019 | Completed |
308 | Testing of steel for the work development of Rajiv Gandhi Indian Institute of Management at Umsawali, Shillong (SH: Construction Design and SITE of sewerage treatment plant including Civil and Electro Mechanical works based on MBBR Technology | CPWD, Shillong , Meghalaya | 23,600.00 | Dr. Deba Kumar Sarma | 14.10.2019 | Completed |